Traffic switch delayed

September 27, 2013 by Randy Keck

In the Sept. 27 issue of The Community News, it was reported that the 1187 traffic switch would occur on Oct 2. Unfortunately, after the paper went to press, we received the following update.

We regret any confusion.

TxDOT and McMahon Construction will delay the scheduled traffic switch on FM 1187 from the night of Wednesday, Oct. 2 to Monday night on Oct. 7, beginning at 8 p.m. due to Aledo High School’s homecoming game on Oct. 4.

The traffic switch on Oct. 7 will move all FM 1187 traffic onto the newly built east side of FM 1187 to allow construction crews to build the new FM 1187 south bound lanes. This plan is expected to create some traffic backups in the area of the Bailey Ranch Road intersection.

Work on the south bound lanes will result in the closing of access to Bankhead Highway off of FM 1187. All traffic wishing to turn onto Bankhead Highway will be detoured to Bailey Ranch Road and then onto Champion’s Drive, which will allow for access to Bankhead Highway. Southbound traffic on FM 1187 wishing to turn right onto Bailey Ranch Road will be able to do so, but without a designated right turn lane at the FM 1187 and Bailey Ranch Road intersection. Northbound traffic on FM 1187 will have a dedicated left turn lane onto Bailey Ranch Road.

1187 traffic to switch Oct. 2

September 19, 2013 by Randy Keck

With construction of FM 1187 into Aledo reaching the halfway point, traffic will be switched to the newly constructed lanes on the east side of the roadway beginning at approximately 8 p.m. on Wednesday, Oct. 2, according to officials with TxDOT and McMahon Construction. The actual switchover could cause some minor delays over a four- hour period from 8 p.m. to midnight, as vehicles are diverted onto the new concrete. In addition, West Oak St. will be closed, and both East Oak St. and Underwood Rd. will reopen for traffic. Access to all businesses will remain available with directional signs posted as crews work to build the new concrete lanes on the west side of FM 1187. Upon completion, FM 1187 will be a four lane divided highway with a median, curbs, gutters, sidewalks and landscaping.

Urban Market

September 6, 2013 by Jennifer Retter

From the City of Aledo:

As you may know, Aledo’s newest attraction, Urban Farmers’ Market, begins tomorrow. The market, showcasing local homegrown produce and art, will be open from 8 a.m. to 1 p.m. Sept. 7 along North Front Street. The Market will take place every Saturday through October. Each Saturday, we will have live music from 9:30 a.m. – noon.

The “upscale” and “intimate” market will offer works of art and other specialty items as well as homegrown local produce from our featuring Producer, Jazbac Farm (a Parker County family farm).

Products offered will include custom knives, belt buckles and jewelry, handmade blankets and pillowcases, organic goat milk soaps and specialty coffees. Mary’s Tamales and Cup & Cake Coffeehouse & Bakery will be there, along with a juicer who sells smoothies.

This is all about a movement in Aledo to make people aware of how shopping locally can stimulate the economy. See you at the Market!

House fire in Aledo

September 4, 2013 by Randy Keck

Randy Keck/The Community NewsAledo, Willow Park, Weatherford and Hudson Oaks Dire Departments responded to a house fire on Wednesday morning on Feedlot Road in Aledo. According to witnesses, the fire may have started in the garage. See the Sept. 6 issue of The Community News for more information.

Road construction progresses

June 21, 2013 by Randy Keck

Joel Kertok of the Parker Counry Judge's Office reports that work continues to progress with the widening and reconstruction of FM 1187 and Aledo Trail.

Crews are expected to continue with the paving of both projects for the next several weeks, with FM 1187 paving taking place from 8 p.m. to 6 a.m. Motorists should be aware that north bound FM 1187 traffic, planning to access I-20 or the east bound service road, is expected to be detoured across the newly paved portions of FM 1187 as they approach the I-20 traffic signal, starting sometime in mid-July.

Current estimates for when work is expected to switch to the west side of FM 1187 and traffic moved completely to the newly constructed east side of FM 1187 in September or October.

FM 1187 Construction Update

May 30, 2013 by Randy Keck

Construction of FM 1187 continues on schedule with crews planning to begin paving the week of June 3. Paving will start at Bankhead and move north to I-20. In order to lessen the impact on motorists, paving will take place at night beginning at 8 p.m. and finishing at 6 a.m. This work is expected to be finished in approximately 3 days, weather permitting. Traffic will be reduced to one lane in the areas where paving is taking place.

Water main break curtails service

May 6, 2013 by Randy Keck

A water main break in the City of Aledo will curtail service from S. Front Street to Barnwell Lane for the two to three hours beginning about 6:15 p.m. Monday, May 6. Aledo Mayor Kit Marshall announced that the Villages of Aledo, Stonebluff and Fairview would have decreased water pressure during that time.

Road closure update

April 26, 2013 by Jennifer Retter

The City of Aledo announced that 1187 will be one-way from Oak to Elm on Monday, April 29, through Thursday, May 2. Underwood at 1187 will be closed beginning Friday (today) or Monday. East Oak at 1187 will remain closed through the summer.

FM 1187 lane closure delayed

April 23, 2013 by Randy Keck

We have received notification from the Texas Department of Transportation that the lane closure on FM 1187 from Oak to Elm will be pushed back a few days in order to accommodate people getting students to school on time for TAKS and STAAR testing.

TxDOT announces FM 1187 reduction

April 22, 2013 by Randy Keck

From the Texas Department of Transportation.

WHEN: Wednesday, April 24, through Wednesday, May 1, daily from 7 a.m. to 7 p.m., weather permitting

WHERE: From Oak Street to Elm Street

ALEDO — Farm-to-Market Road 1187 will be reduced to one lane from Oak Street to Elm Street daily from 7 a.m. to 7 p.m. for the installation of box culverts. Flaggers will direct motorists through the construction zone. Elm Street at FM 1187 will also be closed starting Monday.

The $11.7 million FM 1187 project will expand the roadway to a four-lane divided, concrete roadway with raised medians, curb and gutter and sidewalks.

Completion is estimated for winter 2014. The new roadway will tie into another project known as Aledo Trail, in downtown Aledo.

We appreciate motorist’s patience while crews complete this construction. During construction, alternate routes are encouraged.

Premium Drupal Themes by Adaptivethemes